Headbolt Lane to Rainford Project | United Kingdom
data-transmissionUnited Kingdom of Great Britain and Northern Ireland

Headbolt Lane to Rainford Project | United Kingdom

Operator
Network Rail
Country
United Kingdom of Great Britain and Northern Ireland
Partner
Trackwork
Segment
Main & Regional Line
Products
Data Transmission and Diagnostics
Year
07/2023
Scope of project
Data Transmission

As part of the project to expand Merseyrail services, the operator needed to address the challenge of transmitting indication information over a specific section, spanning from Headbolt Lane to Rainford. In this instance, Frauscher’s technology was utilised to fulfill the data transmission requirements of this project, avoiding expensive and time consuming cabling that would have otherwise been required.

This particular project aimed to extend Merseyrail services from Kirkby Station to a new station at Headbolt Lane. A major requirement consisted of the need to transmit TPWS indications, track circuit interrupter, and arrival and departure interrupter information from Headbolt Lane to Rainford, spanning 7 km. Initial plans involved installing new troughing and cables, a process that would require extensive access planning and would pose significant scheduling challenges due to the tight project timeline. Consequently, the Frauscher data transmission solution was selected as a more efficient alternative to address these requirements.

The Frauscher data transmission solution eliminated the need for new cable installations by leveraging the existing FTNx telecoms network. It enabled safe transmission of various status indications, meeting SIL 4 standards with its QUAD input configuration, which ensured redundancy and reliability without external monitoring. Additionally, the Frauscher Diagnostic System (FDS) provided real-time and historical data access, enhancing system oversight.

Cost-effectiveness

The Frauscher data transmission solution was selected for its competitive cost. One of the key advantages is its ability to minimise overall project costs by removing the necessity to install new cables and additional infrastructure. This feature significantly reduces both initial and long-term costs, making it an economically attractive solution.

Reduced On-Site Activity

The system is designed to enable a significant portion of the work to be completed off-site, which greatly decreases the extent of on-site operations. This approach not only simplifies project management but also helps minimise disruptions to ongoing activities during the construction phase.

Accelerated timeline

The implementation of this solution considerably shortened the overall project duration by eliminating the need for the time-consuming installation of 7 km of new troughing and cabling. This process would have required extensive planning for access and additional time for execution.

A key advantage was the ability to conduct most work off-site, minimising on-site activities and reducing disruptions during construction. This feature simplified project management and accelerated the timeline by avoiding the complex process of laying new cables. Cost-effectiveness was another benefit, as the system reduced overall expenses by using existing infrastructure. Furthermore, fewer civil engineering tasks meant lower risk of delays, particularly during final commissioning. The proven reliability of Frauscher's technology, backed by successful past implementations, reinforced the client's confidence in choosing this solution for the project.

Similar Projects
This might also interest you
1/5
train-detectionChina

CBTC Fallback System on Beijing Metro Lines | China

Beijing metro, one of the busiest lines in the world, was Frauscher’s very first assignment when entering the Chinese market. Due to its utilised capacity, it requires a great level of stability, reliability and performance of the entire signalling system. The Communication Based Train Control System (CBTC) applied here relies on a backup system consisting of fixed automatic train detection systems. Axle counting systems from Frauscher are perfectly suited for the accurate operation of such stand-by systems.
train-detectionUnited Kingdom of Great Britain and Northern Ireland

London to Corby | UK

The project was part of Network Rail’s Midland Main line electrification programme and involved re-signalling between Bedford and Kettering. The goal is the reduction of industry costs and environmental benefits through lighter rolling stock, reduced fuel costs and lower carbon emissions.
train-detectionGermany

Dillinger Hütte | Germany

A new ladder track was required to provide more parking tracks in the steel plant. At the same time, the layout of the dead end tracks were optimised and the efficiency of the whole depot improved by installing the Frauscher Advanced Counter FAdC®i in combination with the wheel sensor RSR180. With the implementation of the Frauscher Diagnostic System FDS, the overall maintenance costs can be significantly reduced.
train-detectionCanada

Edmonton Metro Line | Canada

The Edmonton Metro Line was experiencing significant issues with its newly installed Communications Based Train Control (CBTC) signalling system, which did not perform to the operator‘s expectations. The city was forced to run an incomplete schedule with reduced train speed and frequency which negatively affected commuters and the city of Edmonton in general. Finally in 2019, the operator decided to install a new system in cooperation with Frauscher.
train-detectionDenmark

Renewal signalling FAdC® and RSR123 | Denmark

Banedanmark, the Danish railway infrastructure owner, started replacing the existing signalling system in the Eastern region of Denmark in 2009 to implement the newest proven signalling technology, based on standard industrial hardware components and redundant system configurations. Uniform system interfaces should reduce signalling failures to provide a better reliability and punctuality of the entire network. For this project, Frauscher delivered the Frauscher Advanced Counter FAdC® and the Frauscher Wheel Sensor RSR123.